Written by: Allweathercoating Technical Team
SPRAT- & IRATA-certified · 40+ years Metro Vancouver building envelope experience ·

Every townhouse complex and low-rise strata in Metro Vancouver eventually reaches the roof replacement conversation, and it converges on the same question: asphalt shingle again, or switch to metal.

The way it usually gets argued is cost against lifespan. That framing leaves out most of what actually determines the right answer on a specific building in this region.

Moss is the local variable

This is the factor that changes the comparison in Metro Vancouver and gets left out of the generic advice.

Moss establishes readily on asphalt shingles. It finds the granular surface hospitable, it colonizes shaded north-facing slopes and anything under tree cover, and once established it holds water against the covering continuously. It also grows under the lower edges of shingles and lifts them, which admits water directly.

Metal is a far less welcoming surface. Growth still occurs on shaded metal roofs in this climate, and it sits on the surface rather than working into it, and it does not lift anything.

For a complex under mature trees, which describes a large share of townhouse developments in Burnaby, North Vancouver, and Coquitlam, that difference is a recurring maintenance cost over the roof’s life. It belongs in the comparison alongside the installation price, and the diagnostic value of where the growth appears is covered in the post on moss and biological growth on building exteriors.

Slope constrains the options before price does

Both materials have minimum slopes below which they are not suitable, and metal profiles vary considerably in what they require. A standing seam profile works at lower slopes than many exposed-fastener profiles.

Low-rise strata complexes frequently have complicated roofs: main slopes, lower entry roofs, dormers, and small sections over projections, each at a different pitch. It is common to find that one product cannot serve the whole complex, which turns a clean either-or comparison into a mixed specification.

That has to be established at the assessment stage. A quote priced on the main slopes, with the awkward sections resolved later, is a quote that will generate the change orders described in the post on scope creep and change orders.

Noise depends on the assembly, not the metal

The objection raised in every meeting is rain noise, and it comes from a real experience: metal over open framing on a barn or a carport drums audibly.

Metal over a solid deck, with insulation and a ceiling assembly below, behaves differently. The sound is transmitted through the assembly rather than radiated from a free-vibrating panel, and on a residential building with a normal roof build-up it is a much smaller effect than people expect.

This is worth addressing directly with owners rather than dismissing, because it is the concern that sinks metal proposals at general meetings. The honest answer is that the assembly matters more than the material, and that the specific assembly being proposed should be described rather than assumed.

Snow sheds, and lands somewhere

Metal sheds snow more readily, which reduces the load discussed in the post on snow load and drift on flat roofs.

The snow then goes somewhere. On a townhouse complex, that somewhere is frequently a walkway, an entry, a patio, or the visitor parking. A mass of wet coastal snow sliding off a roof onto a path is a genuine hazard, and it happens on the warm day after the storm rather than during it.

Snow guards manage this and they belong in the original design. Retrofitting them after an incident is possible, and it means penetrating a roof that was installed without them.

Drainage carries a different flow

Water moves faster across metal than across shingle, so the same rainfall produces a higher peak flow at the gutter.

On a complex with existing gutters and downspouts sized for a shingle roof, that is worth checking rather than assuming. Overflowing gutters produce the staining and wall wetting described in the guide on gutters and downspouts on strata buildings, and discovering the capacity issue after the roof is finished is an avoidable expense.

The funding question underneath

For a strata, this is a reserve fund question as much as a roofing one.

A shorter-lived covering means a smaller cost at a shorter interval. A longer-lived one means a larger cost at a longer interval. Those are genuinely different problems for a contingency reserve fund, and which one suits a particular building depends on its current reserve position and its depreciation report projections rather than on which material is better in the abstract.

A strata with a well-funded reserve and a long planning horizon can absorb a larger capital cost that pushes the next replacement well beyond the current owners’ tenure. A strata with a thin reserve facing several other capital items in the same period may be better served by the lower initial cost, even knowing the longer-run arithmetic.

That analysis belongs in the depreciation report update rather than in a roofing quote, and the relationship is set out in the guide on depreciation reports and the building envelope.

Doing one building at a time

Large complexes sometimes phase replacement building by building to spread the cost.

It works. It also produces a complex with two roof types and two appearances, and depending on the interval, that condition can persist for a decade. Owners in the buildings still on the old roof will notice, and owners in the buildings with the new one will have paid the same levy.

It is a legitimate strategy and it needs an explicit decision with the appearance consequence stated plainly, rather than being arrived at by default because that is how the funding worked out.

The deck under both options

Neither material compensates for a deteriorated deck, and on a complex being reroofed the deck condition is the item most likely to change the price after the contract is signed.

Sheathing that has been wet, whether from a failed covering, an ice dam, or the ventilation problems described in the post on blocked soffit vents, has to be replaced. How much of it is unknown until the old covering comes off.

That makes deck replacement the classic concealed condition on a reroofing project, and it should be handled the way all concealed conditions are handled: with a unit rate agreed in the contract and a contingency in the budget, along the lines set out in the post on change orders and scope creep.

Opening a few test areas before tender gives a better estimate of how much is likely, and on a complex with a known history of leaks it is worth the cost.

Ventilation comes with the reroof

A reroof is the practical moment to correct roof cavity ventilation, because the covering is off and the eaves are accessible.

On low-rise strata buildings in this region, the ventilation problems are common and the symptoms get attributed to the roof covering. Replacing the covering without correcting the airflow produces a building that still gets ceiling staining, now under a new roof and a fresh warranty.

The items to address at the same time are soffit vent blockage, baffles at the eave to hold insulation clear, and adequate high-level venting to complete the path. Each is inexpensive during a reroof and disproportionately awkward afterward.

Attic insulation upgrades fall into the same category. If insulation is going to be improved, doing it while the ventilation is being corrected means the baffles go in as part of the same work, which is the sequence that prevents the problem rather than creating it.

What to establish before comparing quotes

Get the slopes measured across the whole complex. Establish the tree cover and shading on each roof. Confirm the deck condition, because both options need a sound deck and neither hides a bad one. Check the gutter capacity. And know where the reserve fund stands.

With those five things known, the comparison is between two real proposals for a specific set of roofs. Without them, it is a debate about materials in general, which is a debate nobody wins.


Sources and further reading

  • Canadian Roofing Contractors Association, CRCA Roofing Specifications Manual, steep-slope roofing systems, referenced 2026
  • Canadian Standards Association, CSA A123 series, asphalt shingle standards, referenced 2026
  • Government of British Columbia, Strata Property Act, depreciation report and contingency reserve fund provisions, referenced 2026
  • Allweathercoating roof assessment records, Metro Vancouver, 2026

Frequently Asked Questions

Which lasts longer, shingles or metal?

Metal generally has a longer service life than asphalt shingle in this climate, which is the main argument for it. How much longer depends on the specific product, the coating system on the metal, and the exposure, so the comparison should use the actual products being quoted rather than category averages.

How does moss affect the choice?

Significantly in Metro Vancouver. Moss establishes readily on shingles, particularly on shaded north-facing slopes and under trees, and it holds water against the covering and lifts the edges. Metal is far less hospitable to it, which reduces a recurring maintenance cost that many stratas underestimate.

Is metal roofing noisy in the rain?

It can be, and it depends heavily on the assembly underneath. Metal over a solid deck with insulation behind it is not the drumming sound people picture, which comes from metal over open framing. On an occupied building the assembly matters more than the material.

Does roof slope limit the options?

Yes. Both materials have minimum slopes below which they are not suitable, and metal profiles vary considerably in what slope they require. A complex low-rise roof with several different slopes may not be able to use one product across all of it.

What about cost?

Metal generally costs more to install and less over its life, which is the standard trade. What matters for a strata is how that maps onto the contingency reserve fund and the depreciation report cycle, because a larger cost at a longer interval is a different funding problem from a smaller cost more often.

Does metal help with snow?

Snow sheds more readily off metal, which reduces load but creates a different hazard where snow can slide onto walkways, entries, and parked cars. Snow guards address this and they need to be part of the design rather than added after the first incident.

Can we replace one building in a complex at a time?

Physically yes, and it creates a complex with two different roof types and appearances. Some stratas accept that to spread the cost, and it needs an explicit decision rather than drifting into it, because the appearance difference is permanent and visible.

How does each material handle repairs?

Individual shingles are straightforward to replace and matching the colour of weathered shingles is imperfect. Metal panel repairs are more involved because panels interlock, and a damaged panel in the middle of a run is harder to swap than a shingle.

Do gutters and drainage change between the two?

Water moves faster off metal, so gutters see higher peak flow from the same rainfall. On a complex with existing gutters sized for shingle, that is worth checking before assuming the drainage carries over unchanged.

Which is better for a townhouse complex specifically?

There is no single answer, because it depends on slope, tree cover, access for future maintenance, and how the strata funds capital work. A complex under heavy tree cover with a well-funded reserve leans one way, and a complex with simple accessible roofs and a thin reserve leans the other.